Sunday, January 31, 2010

LRT service from Ampang to be extended soon



PETALING JAYA -- Transport Minister Datuk Seri Ong Tee Keat said today his ministry plans to expand the light rail transit (LRT) service from Ampang soon.
He said the ministry received feedback from the public requesting it to include and improve the Ampang line in the expansion plan, especially around Puchong and Serdang area.
"The ministry has just completed tackling the extension of the rail service from Kelana Jaya to Subang.
"We will be conducting the same process as we did when tackling the Kelana Jaya extension, including conducting public hearing and also town hall meetings, for the expansion of the rail service from Ampang to Puchong-Serdang," he said.
He was speaking to reporters after launching the "Hope and Train 2009/2010 Appreciation Ceremony" at Taylor's University College new campus here.
Ong said the ministry received an overwhelming support for the expansion of the Kelana Jaya-Subang rail last year and decided to conduct the same process for the Ampang line.
He also said that the public also wanted the LRT service to be improved including shortening the waiting time for coaches.
"As improving public transportation is one of priorities in the National Key Result Area (NKRA), it is the responsibilities of the ministry to improve the LRT system," he said.
The Ampang LRT line extension will begin from the Sri Petaling Station passing through Kinrara and Puchong before ending at Putra Heights, covering a distance of 17.7km with 13 new stations.
Asked whether the Ampang LRT line would also be using new coaches like the Kelana Jaya LRT line, Ong said the ministry was looking into it.
The extensions for the Kelana Jaya and Ampang LRT lines are estimated to cost RM7 billion and managed by Syarikat Prasarana Negara Berhad (SPNB).


source: Bernama January 31st, 2010

Saturday, January 16, 2010

MPSJ looks at long-term plan to end Puchong traffic woes

WHILE the Subang Jaya Municipal Council (MPSJ) has yet to collect sufficient funds to fully implement the traffic system upgrade plan in Taman Perindustrian Puchong Utama, several efforts are being made to alleviate the traffic situation.
It includes traffic lights for Jalan Utama 2, which will also be widened.


Plenty of space: The plot of vacant land will be used to widen the road in an effort to alleviate congestion.

MPSJ councillor Ng Sze Han said 10 developers, which had projects in the area, are supposed to contribute to the RM20mil fund according to the size and progress of their developments.
So far, only 38.5% (or about RM7.7mil) has been collected from seven developers and only one of them has fully settled its contribution.
“The rest are still going on with their projects, while three other haven’t started their projects yet,” Ng, who sits on the infrastructure committee, said.
The main part of the upgrade plan involves the construction of an interchange from the Damansara-Puchong Expressway (LDP) into Jalan Utama 2 and several upgrade works on Jalan Utama 2.
Ng said the interchange would cost RM17mil and the initial planning could only start when the council had collected at least RM10mil.
The council had also used part of the money to install traffic lights at the junction of Jalan Utama 2 and Persiaran Puchong Perdana last year.
It is also looking at widening Jalan Utama 2 by turning a part of the vacant land into lanes.
Meanwhile, Litrak, the LDP highway concessionaire, has agreed to upgrade the Puchong Perdana Interchange following requests from the MPSJ.
A slip road would be constructed at the traffic light junction underneath the flyover in both directions (from Tractors and Puchong Jaya Selatan toll).
Persiaran Puchong Perdana would also be widened to have one extra lane at both directions.
Litrak communications head Bhavani Krishna Iyer said Litrak would start the work as soon as it received the approval.
“Some of the land we will be working on belongs to the council and we need to wait for the approval. It will take about nine months for the work to be completed,” she said.
Bhavani stressed that this was not a permanent solution and the Puchong Utama Interchange must be pushed through for a long-term solution to the traffic woes.
As-salam Mosque women’s bureau chief Noorhanim Ismail, whose mosque is located along Persiaran Puchong Perdana, welcomed the upgrade plan.
Mohd Ariffuddin Kamari from the MPSJ Engineering Department said the council would seek opinions from the residents regarding the sound barriers.
“The residents can let us know what type of sound barriers they prefer and we will forward their views to Litrak,” he said.

source: The Star January 16, 2010